Two federal tracks. The summit deal plate is the 167-project investor prospectus (145 catalogued here). The fast-track list is the Major Projects Office roster (19 here), three of which are in the Building Canada Act listing process. 9 projects are on both; 136 are pitched to investors without a fast-track referral; 10 are fast-tracked but not in the book.
| Project | Prov | Sector | Stage | Summit | Fast-track | BCA | Capex (US$) |
|---|---|---|---|---|---|---|---|
| Port of Churchill Plus | MB | Marine & Port | Advanced / FEED | ● | ● | · | US$57B |
| Alto High-Speed Rail (Toronto–Québec City) | ON/QC | Transportation | Advanced / FEED | ● | · | · | US$44B – US$66B |
| Wind West | NS | Clean Energy | Early / concept | ● | · | · | US$44B |
| Churchill Falls / Gull Island Hydro | NL | Power & Utilities | Advanced / FEED | · | · | · | US$37B |
| West Coast Oil Pipeline | AB→BC | Conventional Energy | Early / concept | ● | ● | · | US$35B |
| Ksi Lisims LNG + PRGT Pipeline | BC | Conventional Energy | Shovel-ready | ● | ● | · | US$29B |
| LNG Canada Phase 2 | BC | Conventional Energy | Advanced / FEED | · | ● | · | US$24B |
| Kino Aski LNG (cross-Canada to Québec port) | QC | Conventional Energy | Early / concept | ● | · | · | US$23B |
| Deep Geological Repository (Ignace) | ON | Power & Utilities | Feasibility / permitting | · | ● | ● | US$19B |
| Darlington New Nuclear (SMR ×4) | ON | Power & Utilities | Under construction | · | ● | · | US$15B |
| Conawapa Hydro (revived) | MB | Power & Utilities | Early / concept | · | · | · | US$13B – US$15B |
| EVREC Green Energy Hub | NL | Clean Energy | Advanced / FEED | ● | · | · | US$11B |
| BW Velora — Redcliff (Medicine Hat) | AB | Digital Technology | Advanced / FEED | ● | · | · | US$11B |
| Woodfibre LNG Expansion | BC | Conventional Energy | Early / concept | ● | · | · | US$9.9B |
| Calgary–Edmonton High-Speed Rail | AB | Transportation | Early / concept | ● | · | · | US$8.0B |
| Low-Carbon Synthetic Gasoline Facilities (×2) | AB | Conventional Energy | Advanced / FEED | ● | · | · | US$6.0B – US$7.0B |
| Mactaquac Life Achievement Project | NB | Power & Utilities | Advanced / FEED | ● | · | · | US$5.1B – US$6.6B |
| PowerCo (Volkswagen) Gigafactory | ON | Advanced Manufacturing | Under construction | ● | · | · | US$5.1B |
| North Atlantic Green Energy Hub | NL | Clean Energy | Advanced / FEED | ● | · | · | US$5.1B |
| Nova Scotia Renewable Energy Park | NS | Clean Energy | Advanced / FEED | ● | · | · | US$4.5B |
| North Coast Transmission Line | BC | Power & Utilities | Under construction | · | ● | · | US$4.4B |
| Genesee Energy Campus | AB | Clean Energy | Advanced / FEED | ● | · | · | US$2.0B – US$6.0B |
| Beacon Data Centres — Spruce Lake | NB | Digital Technology | Advanced / FEED | ● | · | · | US$3.9B |
| VIA Rail fleet — 313 cars (Thunder Bay) | ON | Transportation | Under construction | ● | · | · | US$3.4B |
| Berg Copper | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$3.4B |
| Kivalliq Hydro-Fibre Link | NU/MB | Power & Utilities | Advanced / FEED | ● | · | · | US$3.4B |
| Prince Rupert E-Fuels | BC | Clean Energy | Early / concept | ● | · | · | US$1.3B – US$5.3B |
| Projet Mauricie | QC | Clean Energy | Advanced / FEED | ● | · | · | US$3.0B |
| Kami Iron Ore | NL | Minerals & Metals | Feasibility / permitting | ● | · | · | US$3.0B |
| Casino Copper-Gold | YT | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.9B |
| Roberts Bank Terminal 2 | BC | Transportation | Advanced / FEED | ● | ● | · | US$2.6B |
| Clearwater (direct lithium extraction) | AB | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.5B |
| Baptiste Nickel | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.2B |
| Strange Lake Rare Earths | QC/NL | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.2B |
| Prairie Connector Pipeline | AB→US | Conventional Energy | Advanced / FEED | ● | · | · | US$2.1B |
| Nechalacho Basal Rare Earth | NT | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.1B |
| Crawford Nickel | ON | Minerals & Metals | Advanced / FEED | ● | ● | · | US$2.0B |
| Pine Point Zinc-Lead | NT | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.0B |
| Yellowhead Copper | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$2.0B |
| Via TWO (synthetic graphite) | ON | Minerals & Metals | Advanced / FEED | ● | · | · | US$2.0B |
| Courant Project (H₂ + hydro for ammonium nitrate) | QC | Clean Energy | Advanced / FEED | ● | · | · | US$1.8B – US$2.1B |
| 10 GW Integrated Gigafactory Campus | ON | Clean Energy | Early / concept | ● | · | · | US$1.9B |
| Red Chris Mine Expansion | BC | Minerals & Metals | Advanced / FEED | · | ● | · | US$1.9B |
| BW Velora — Grande Prairie | AB | Digital Technology | Advanced / FEED | ● | · | · | US$1.8B |
| Contrecœur Container Terminal | QC | Marine & Port | Advanced / FEED | · | ● | · | US$1.7B |
| Port Alberni Transshipment Hub (PATH) | BC | Marine & Port | Early / concept | ● | · | · | US$1.5B – US$1.8B |
| Rook I Uranium | SK | Minerals & Metals | Under construction | ● | · | · | US$1.6B |
| Port of Belledune Iron-Ore Terminal | NB | Marine & Port | Early / concept | ● | · | · | US$1.5B |
| Loki Flake Graphite | SK | Minerals & Metals | Feasibility / permitting | ● | · | · | US$1.4B |
| Wicheeda Rare Earth | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$1.4B |
| Manitoba Renewable Fuel Production Facility | MB | Clean Energy | Advanced / FEED | ● | · | · | US$1.4B |
| Nicola Wind Energy Project | BC | Clean Energy | Advanced / FEED | ● | · | · | US$1.4B |
| Matawinie Graphite Mine | QC | Minerals & Metals | Advanced / FEED | · | ● | · | US$1.3B |
| The Alberta Project (forestry residuals → RNG) | AB | Clean Energy | Advanced / FEED | ● | · | · | US$1.3B |
| Port of Québec Modernization | QC | Marine & Port | Advanced / FEED | ● | · | · | US$1.2B |
| PLS (Triple R) Uranium | SK | Minerals & Metals | Advanced / FEED | ● | · | · | US$1.2B |
| Nova Scotia Grid Infrastructure (2×300 MW) | NS | Clean Energy | Advanced / FEED | ● | · | · | US$1.2B |
| Bay d'Espoir Hydro Upgrade | NL | Clean Energy | Feasibility / permitting | ● | · | · | US$1.1B |
| Shaakichiuwaanaan (Li-Ta-Cs) | QC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$1.1B |
| Troilus Copper-Gold | QC | Minerals & Metals | Advanced / FEED | ● | · | · | US$1.1B |
| Atlantic Canada E-Fuels | NB/NS | Clean Energy | Early / concept | ● | · | · | US$1.0B |
| Minago Critical Minerals | MB | Minerals & Metals | Feasibility / permitting | ● | · | · | US$1.0B |
| Novaporte | NS | Marine & Port | Advanced / FEED | ● | · | · | US$1.0B |
| Sterling Shipyards (bulk export terminal) | BC | Marine & Port | Early / concept | ● | · | · | US$1.0B |
| Xanadu — Large-Scale Quantum Machine | ON | Digital Technology | Early / concept | ● | · | · | US$949M |
| Spanish Mountain Gold | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$892M |
| Dumont Nickel | QC | Minerals & Metals | Shovel-ready | ● | · | · | US$881M |
| Prairie Lithium | SK | Minerals & Metals | Under construction | ● | · | · | US$881M |
| Grays Bay Road and Port | NU | Marine & Port | Advanced / FEED | ● | ● | ● | US$850M |
| North Island Copper-Gold-Mo | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$846M |
| Ashram Rare Earths & Fluorspar | QC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$840M |
| Alberta Industrial Heartland 1.0 (waste-to-energy + CCS) | AB | Clean Energy | Shovel-ready | ● | · | · | US$800M |
| Marguerite Lake Energy (CAES) | AB | Power & Utilities | Advanced / FEED | ● | · | · | US$790M |
| Cariboo Gold | BC | Minerals & Metals | Shovel-ready | ● | · | · | US$764M |
| Project Oqwatn (St. John's Dockyard) | NL | Marine & Port | Advanced / FEED | ● | · | · | US$750M |
| Lawyers-Ranch Gold-Silver | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$736M |
| Moblan Lithium | QC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$722M |
| East Calgary Carbon Sequestration Hub | AB | Clean Energy | Feasibility / permitting | ● | · | · | US$720M |
| NICO Cobalt-Gold-Bismuth-Copper | NT | Minerals & Metals | Advanced / FEED | ● | · | · | US$720M |
| Coffee Gold | YT | Minerals & Metals | Advanced / FEED | ● | · | · | US$718M |
| PAK Lithium | ON | Minerals & Metals | Feasibility / permitting | ● | · | · | US$682M |
| LFP Cathode Active Materials Plant | QC | Clean Energy | Advanced / FEED | ● | · | · | US$673M |
| Covenant Energy (renewable diesel + SAF) | SK | Clean Energy | Advanced / FEED | ● | · | · | US$653M |
| Xanadu — Quantum Manufacturing Facility | ON | Digital Technology | Advanced / FEED | ● | · | · | US$652M |
| Boardwalk Lithium Brine | SK | Minerals & Metals | Feasibility / permitting | ● | · | · | US$600M |
| Sisson Tungsten-Molybdenum | NB | Minerals & Metals | Advanced / FEED | ● | ● | · | US$600M |
| Scully Manganese Sulphate | NL | Minerals & Metals | Feasibility / permitting | ● | · | · | US$600M |
| Canadian Uranium Conversion Facility | TBD | Minerals & Metals | Advanced / FEED | ● | · | · | US$575M |
| Vegreville Project (straw → SAF) | AB | Clean Energy | Advanced / FEED | ● | · | · | US$450M – US$600M |
| Project Titan (sulphate of potash) | SK | Minerals & Metals | Shovel-ready | ● | · | · | US$150M – US$900M |
| Wheeler River Uranium | SK | Minerals & Metals | Under construction | ● | · | · | US$504M |
| Sweetwater Wind Farm | BC | Clean Energy | Feasibility / permitting | ● | · | · | US$500M |
| Bissett Creek Graphite + BAM | ON | Minerals & Metals | Feasibility / permitting | ● | · | · | US$500M |
| Kudz Ze Kayah | YT | Minerals & Metals | Advanced / FEED | ● | · | · | US$492M |
| Rose Lithium-Tantalum | QC | Minerals & Metals | Shovel-ready | ● | · | · | US$486M |
| Northern Spruce (pulp-mill BECCS) | AB | Clean Energy | Advanced / FEED | ● | · | · | US$420M – US$500M |
| Touquoy Mine Renewable Energy Hub | NS | Clean Energy | Early / concept | ● | · | · | US$450M |
| Prairie Silica | MB | Minerals & Metals | Advanced / FEED | ● | · | · | US$400M – US$500M |
| Blue & Turquoise Hydrogen / Methanol Modular Plant | AB | Conventional Energy | Advanced / FEED | ● | · | · | US$440M |
| Great Atlantic Salt | NL | Minerals & Metals | Shovel-ready | ● | · | · | US$440M |
| Pozzolan & SCMs | QC | Minerals & Metals | Advanced / FEED | ● | · | · | US$432M |
| McIlvenna Bay Copper | SK | Minerals & Metals | Under construction | · | ● | · | US$402M |
| Green Bay Copper-Gold | NL | Minerals & Metals | Feasibility / permitting | ● | · | · | US$365M |
| Photonic — Vanguard Quantum Chip Plant | BC | Digital Technology | Advanced / FEED | ● | · | · | US$365M |
| Melford International Terminal | NS | Marine & Port | Shovel-ready | ● | · | · | US$357M |
| H2 Gateway hydrogen liquefaction | BC | Clean Energy | Advanced / FEED | ● | · | · | US$350M |
| Prairie Creek Silver-Zinc (PC Silver) | NT | Minerals & Metals | Shovel-ready | ● | · | · | US$350M |
| Qik Port (Qikiqtarjuaq) | NU | Marine & Port | Shovel-ready | ● | · | · | US$350M |
| Deep Sky One (direct air capture) | AB | Clean Energy | Advanced / FEED | ● | · | · | US$328M |
| Prairie Economic Gateway | AB | Marine & Port | Advanced / FEED | ● | · | · | US$320M |
| Saguenay Industrial & Port Zone | QC | Marine & Port | Under construction | ● | · | · | US$290M |
| Alberta Critical Minerals Recovery & REE Refining | AB | Minerals & Metals | Feasibility / permitting | ● | · | · | US$216M – US$360M |
| Trenton Energy Storage | NS | Clean Energy | Advanced / FEED | ● | · | · | US$275M |
| Bécancour Battery Material Plant | QC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$267M |
| Yellowknife Lithium + Conversion | NT/AB | Minerals & Metals | Feasibility / permitting | ● | · | · | US$259M |
| Quintette Underground + Trend-Roman | BC | Minerals & Metals | Advanced / FEED | ● | · | · | US$251M |
| Gold Creek Industrial Complex | BC | Conventional Energy | Shovel-ready | ● | · | · | US$250M |
| Kardium (medtech commercialization) | BC | Advanced Manufacturing | Advanced / FEED | ● | · | · | US$250M |
| Bécancour Cobalt Facility | QC | Minerals & Metals | Advanced / FEED | ● | · | · | US$217M – US$250M |
| Goldboro Gold | NS | Minerals & Metals | Shovel-ready | ● | · | · | US$217M |
| Canadian Showcase (diluent-free heavy oil upgrading) | SK | Conventional Energy | Advanced / FEED | ● | · | · | US$210M |
| 15 Mile Processing Hub | NS | Minerals & Metals | Feasibility / permitting | ● | · | · | US$202M |
| Enfield RTP Clean Fuel Facility | NS | Clean Energy | Shovel-ready | ● | · | · | US$200M |
| Western Canada Single Super Phosphate | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$200M |
| New Polaris (gold-antimony) | BC | Minerals & Metals | Advanced / FEED | ● | · | · | US$200M |
| Thompson Nickel Mine | MB | Minerals & Metals | Under construction | ● | · | · | US$200M |
| Minto Copper/Gold/Silver (restart) | YT | Minerals & Metals | Feasibility / permitting | ● | · | · | US$200M |
| Bull Arm Industrial Marine Centre | NL | Marine & Port | Advanced / FEED | ● | · | · | US$180M – US$220M |
| Micro-Modular Reactor Platform | Multi | Power & Utilities | Early / concept | ● | · | · | US$178M |
| Eauclaire FORCE Tidal Array | NS | Clean Energy | Advanced / FEED | ● | · | · | US$175M |
| Lac Knife Graphite | QC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$170M |
| SRC Minerals-to-Magnet | SK | Minerals & Metals | Early / concept | ● | · | · | US$170M |
| Red Mountain & Premier Gold | BC | Minerals & Metals | Feasibility / permitting | ● | · | · | US$160M |
| Project Northern Lights (small-scale LNG) | AB | Conventional Energy | Shovel-ready | ● | · | · | US$60M – US$250M |
| North Star Project (BECCS) | SK | Clean Energy | Advanced / FEED | ● | · | · | US$135M – US$170M |
| Gasia Homestead Diluent Recovery & Partial Upgrader | AB | Conventional Energy | Advanced / FEED | ● | · | · | US$150M |
| Nova Scotia Spaceport (Canso) | NS | Advanced Manufacturing | Advanced / FEED | ● | · | · | US$146M |
| Canadian Sovereign Magnesium Platform | QC | Minerals & Metals | Advanced / FEED | ● | · | · | US$14M – US$264M |
| Canada's First Helium Liquefaction | SK | Minerals & Metals | Shovel-ready | ● | · | · | US$100M |
| True North Gold | NU | Minerals & Metals | Shovel-ready | ● | · | · | US$42M |
| Scotia Mine (zinc-lead) | NS | Minerals & Metals | Advanced / FEED | ● | · | · | US$25M |
| Point Tupper Green Hydrogen | NS | Clean Energy | Advanced / FEED | ● | · | · | not disclosed |
| New Nuclear in New Brunswick | NB | Clean Energy | Advanced / FEED | ● | · | · | not disclosed |
| MacTung Tungsten | YT | Minerals & Metals | Feasibility / permitting | ● | · | · | not disclosed |
| Ring of Fire (Juno Corp.) | ON | Minerals & Metals | Early / concept | ● | · | · | not disclosed |
| NEXT — Atlantic Hub Container Terminal (Halifax) | NS | Marine & Port | Shovel-ready | ● | · | · | not disclosed |
| Port Saint John Optimization | NB | Marine & Port | Advanced / FEED | ● | · | · | not disclosed |
| ScotiaPort | NS | Marine & Port | Early / concept | ● | · | · | not disclosed |
| Bruce C | ON | Power & Utilities | Early / concept | ● | · | · | not disclosed |
| Leif Erikson Trans-Atlantic Fibre | NL→NO | Digital Technology | Advanced / FEED | ● | · | · | not disclosed |
| Canadian Photonic Fabrication Centre | ON | Digital Technology | Advanced / FEED | ● | · | · | not disclosed |
| Telesat (minority equity stake) | ON | Digital Technology | Under construction | ● | · | · | not disclosed |
| Vianode Synthetic Graphite Plant | ON | Advanced Manufacturing | Advanced / FEED | ● | · | · | not disclosed |
| Mackenzie Valley Highway | NT | Transportation | Advanced / FEED | ● | ● | ● | not disclosed |
| Arctic Economic & Security Corridor | NT | Transportation | Early / concept | ● | ● | · | not disclosed |
| Iqaluit Nukkiksautiit Hydro | NU | Power & Utilities | Early / concept | · | ● | · | not disclosed |
| Taltson Hydro Expansion | NT | Power & Utilities | Feasibility / permitting | · | ● | · | not disclosed |