Marine & Port · QC · #46 of 131 disclosed prospectus tickets

Port of Québec Modernization

Summit deal plate

2026–2035 asset renewal, deep-water docks

At a glance

Proponent
Québec Port Authority
Capex (as printed)
US$1.2B
Capex (US$, midpoint)
US$1.2B
Stage
Advanced / FEED
Location
46.82°N, 71.20°W
Summit deal plate
Yes — in the 167-project prospectus pitched Sept 14–15 2026
Fast-track list
No MPO referral on record
Project location.

Modelled GDP contribution Modelled

Build 2028–2030 at 55% construction value-added, then 6% of capex per year operating. Peak US$227M/yr · cumulative 2026–40 US$1.4B.

US$0MUS$100MUS$200M2026203020352040

Connectivity · nearest existing infrastructure

Straight-line distance from the project point to the nearest vertex of each network layer.

Railway7 km
Major highway2 km
Transmission ≥230 kV2 km
Pipeline233 km
PortQuebec2 km
Generating stationRivière-du-Moulin Wind (350 MW)145 km
City >50kQuébec4 km

Nearest other projects

Pozzolan & SCMsMinerals & Metals15 km
Bécancour Cobalt FacilityMinerals & Metals101 km
LFP Cathode Active Materials PlantClean Energy106 km
Bécancour Battery Material PlantMinerals & Metals110 km
Courant Project (H₂ + hydro for ammonium nitrate)Clean Energy117 km

Also in Quebec

Kino Aski LNG (cross-Canada to Québec port)Early / conceptUS$23B
Projet MauricieAdvanced / FEEDUS$3.0B
Strange Lake Rare EarthsFeasibility / permittingUS$2.2B
Courant Project (H₂ + hydro for ammonium nitrate)Advanced / FEEDUS$1.8B – US$2.1B
Contrecœur Container TerminalAdvanced / FEEDUS$1.7B
Matawinie Graphite MineAdvanced / FEEDUS$1.3B

Open on the Dealbook map · Open the Infrastructure Atlas · Back to the register