Digital Technology · AB · #37 of 131 disclosed prospectus tickets

BW Velora — Grande Prairie

Summit deal plate

150 MW data centre

At a glance

Proponent
BW Velora (Norway)
Capex (as printed)
C$2.4B C$ source
Capex (US$, midpoint)
US$1.8B
Stage
Advanced / FEED
Location
55.17°N, 118.80°W
Summit deal plate
Yes — in the 167-project prospectus pitched Sept 14–15 2026
Fast-track list
No MPO referral on record
Project location.

Modelled GDP contribution Modelled

Build 2028–2030 at 55% construction value-added, then 10% of capex per year operating. Peak US$321M/yr · cumulative 2026–40 US$2.6B.

US$0MUS$100MUS$200MUS$300M2026203020352040

Connectivity · nearest existing infrastructure

Straight-line distance from the project point to the nearest vertex of each network layer.

Railway7 km
Major highway376 km
Transmission ≥230 kV174 km
Pipeline0 km
PortOcean Falls662 km
Generating stationSite C (1,100 MW)174 km
City >50kPrince George291 km

Nearest other projects

Gold Creek Industrial ComplexConventional Energy112 km
Quintette Underground + Trend-RomanMinerals & Metals148 km
Sweetwater Wind FarmClean Energy156 km
Northern Spruce (pulp-mill BECCS)Clean Energy212 km
Wicheeda Rare EarthMinerals & Metals214 km

Also in Alberta

West Coast Oil PipelineEarly / conceptUS$35B
BW Velora — Redcliff (Medicine Hat)Advanced / FEEDUS$11B
Calgary–Edmonton High-Speed RailEarly / conceptUS$8.0B
Low-Carbon Synthetic Gasoline Facilities (×2)Advanced / FEEDUS$6.0B – US$7.0B
Genesee Energy CampusAdvanced / FEEDUS$2.0B – US$6.0B
Clearwater (direct lithium extraction)Feasibility / permittingUS$2.5B

Open on the Dealbook map · Open the Infrastructure Atlas · Back to the register