Minerals & Metals · ON · #72 of 131 disclosed prospectus tickets

PAK Lithium

Summit deal plate

200 ktpa spodumene + 20 ktpa Li₂CO₃

At a glance

Proponent
Frontier Lithium
Capex (as printed)
US$682M
Capex (US$, midpoint)
US$682M
Stage
Feasibility / permitting
Location
51.20°N, 93.50°W
Summit deal plate
Yes — in the 167-project prospectus pitched Sept 14–15 2026
Fast-track list
No MPO referral on record
Project location.

Modelled GDP contribution Modelled

Build 2030–2032 at 55% construction value-added, then 15% of capex per year operating. Peak US$125M/yr · cumulative 2026–40 US$1.1B.

US$0MUS$50MUS$100M2026203020352040

Connectivity · nearest existing infrastructure

Straight-line distance from the project point to the nearest vertex of each network layer.

Railway135 km
Major highway360 km
Transmission ≥230 kV252 km
Pipeline174 km
PortChurchill843 km
Generating stationGrand Rapids (MB) (479 MW)453 km
City >50kWinnipeg298 km

Nearest other projects

Deep Geological Repository (Ignace)Power & Utilities227 km
Prairie SilicaMinerals & Metals270 km
Manitoba Renewable Fuel Production FacilityClean Energy369 km
VIA Rail fleet — 313 cars (Thunder Bay)Transportation436 km
Minago Critical MineralsMinerals & Metals516 km

Also in Ontario

Alto High-Speed Rail (Toronto–Québec City)Advanced / FEEDUS$44B – US$66B
Deep Geological Repository (Ignace)Feasibility / permittingUS$19B
Darlington New Nuclear (SMR ×4)Under constructionUS$15B
PowerCo (Volkswagen) GigafactoryUnder constructionUS$5.1B
VIA Rail fleet — 313 cars (Thunder Bay)Under constructionUS$3.4B
Crawford NickelAdvanced / FEEDUS$2.0B

Open on the Dealbook map · Open the Infrastructure Atlas · Back to the register